AST SpaceMobile's Blacklift rocket plan meets doubts over its launch pad and engines

AST says its three-stage reusable rocket will fly in late 2028. Virginia's spaceport says talks exclude the pad AST cites, and Firefly's Miranda engine is still in qualification.

FrontierPublished
What happened
At a New York event on 12 November, AST SpaceMobile gave technical details of Blacklift, the reusable rocket it plans to launch its BlueBird satellites.
What’s new
AST described a three-stage, all-composite design with Firefly engines and repeated its target of a first flight in late 2028.
Why it matters
AST says it is building its own rocket because it cannot get enough launches on time for its direct-to-device satellite constellation.

AST SpaceMobile, which is building a constellation of direct-to-device BlueBird satellites, used a 12 November event in New York to set out its case for Blacklift. The company first announced the rocket on 6 November. According to SpaceNews, chief executive Abel Avellan said AST is entering the launch business only because it cannot secure enough timely launches for its satellites.

What AST says Blacklift will be

AST says Blacklift will lift 20 tons to low Earth orbit, enough for up to five BlueBird satellites per flight. The rocket will carry only AST payloads, and the company is aiming for two launches a month. The design has three stages: seven Firefly Miranda engines on the first stage, two Firefly Vira engines on the second and one Vira on the third. Avellan argues that a third stage lets the reusable first stage fly lower and return more easily. SpaceNews notes that existing and in-development reusable rockets, including Falcon 9 and New Glenn, use two stages. According to SpaceNews, the event showed no rocket hardware, only engine videos and animations.

AST says buying engines rather than developing its own makes a late-2028 first flight feasible. Avellan told the audience, "We're starting this program on third base." The $1.3 billion Firefly contract covers engines for the first three rockets, a license for AST to build its own engines, and engineering services.

Disputed launch site and engine readiness

AST says its early flights will use the Wallops Island, Virginia, pad built for Northrop Grumman's Antares. An AST slide said that pad was already being upgraded for Miranda engines, and Ars Technica relays the same plan. However, a Virginia Spaceport Authority spokesperson told SpaceNews that its preliminary talks with AST do not cover Pad 0-A, the Antares pad. SpaceNews reports that AST's remaining options at Wallops, renovating Pad 0-B or building a new pad, would cost more and take longer.

Avellan described Miranda as ready to fly. Ars Technica reports that the engine has not finished its formal qualification campaign or flown on an orbital rocket. According to Ars, Firefly chief executive Jason Kim said qualification testing is still underway. Ars adds that little is publicly known about the readiness of the Vira upper-stage engine.

Composite tanks as a risk

AST says it is making composite tanks at its Midland, Texas, factory and expects to finish 10 for testing by January. Both outlets cite Rocket Lab's troubles as a caution. SpaceNews reports that a Neutron composite tank was damaged in qualification testing in January and that another tank problem in October pushed Neutron's first launch into 2027. Ars Technica calls AST's timeline preposterous. It argues that tanks, software, avionics, stage separation and production scaling can all delay a rocket, not just engines.